Developing Preliminary Commissioning Plan

The Commissioning Plan establishes the framework for how commissioning will be handled and managed on a given proj­ect. This includes a discussion of the commissioning process, schedule, team, team member responsibilities, communication structures, and a general description of the systems to be com­missioned. This preliminary version of the plan shall be devel­oped by the GSA PM in conjunction with the Customer Agency. The suggested structure of the Commissioning Plan is as follows. All information in the Commissioning Plan must be project specific.

Legend

L = Lead P = Participate S = Support I = Inform A = Approve V = Verify

GSA

Project

Manager

GSA

Operating

Personnel

Customer

Agency

Reps

GSA

Technical

Experts

CM

Construction

Contractor

CxA

A/E

Planning Stage

Identify Commissioning Team

L/A

S

S

P/S

Develop Owner’s Project Requirements

L/A

S

s

S

Develop preliminary commissioning scope

L

s

s

P/S

Develop Preliminary Commissioning Plan

L

s

s

S

Establish budget for all Cx work & integrate costs for commissioning into project budget

L

s

s

S

Include time for Cx in initial project schedule

L

I

I

I

Include Cx responsibilities in A/E & CM scope of services

L/A

s

S

Quality — From Theory to Reality 261

Legend

L = Lead P = Participate S = Support I = Inform A = Approve V = Verify

GSA

Project

Manager

GSA

Operating

Personnel

Customer

Agency

Reps

GSA

Technical

Experts

CM

Construction

Contractor

CxA

A/E

Design Stage

Contract fro Commissioning Agent Service

L/A

P

P

P

L

Hold Design Stage Cx meeting

P

P

P

P

P

L

P

Identify project specific responsibilitie

L

P

P

S

s

P

P

Review Owner’s Project Requirements documentation for completeness & clarit

S

S

I

I

L

I

Develop Basis of Desig

A

P

P

S/A

I

I

L

Perform focused Cx reviews of design drawings & specification

P

P

P

S

L

S

Perform project constructability review

P

I/P

L

i/s

S

262 Construction Management for Industrial Projects

Incorporate appropriate changes to contract documents based upon design review

A

P

P

I

I

L

L

Refine Owner’s Project Requirements based upon Design Stage Decision

A

P

P

S

I

L

S

Create Cx specifications including testing protocols for all commissioned equip./system

I

I

I

P/S

s

L

s

Integrate Cx activities into project schedul

A

I

I

Coordinate integration issues & responsibilities between equipment, systems & discipline

A

I

I

P/S

s

V

L

Update Commissioning PlaN

A

I

I

I

s

L

I

Incorporate commissioning requirements into Construction

Contractor’s Scope of WorK

A

I

L

S

S

Construction Stag

Revise Commissioning Plan as necessary

Quality — From Theory to Reality 263

Legend

L = Lead P = Participate S = Support I = Inform A = Approve V = Verify

GSA

Project

Manager

GSA

Operating

Personnel

Customer

Agency

Reps

GSA

Technical

Experts

CM

Construction

Contractor

CxA

A/E

Review submittals applicable to equipment/ systems being commissioned

Review project submittals for construction quality control & specification conformance

A

I

I

I

I

S

I

L

Develop functional test procedures and documentation formats for all commissioned equipment & assemblies

I

P

A

S

S

L

Include Cx requirements and activities in each purchase order and subcontract written

I

I/P

A

L

s

V

Develop construction checklists for equipment/ systems to be commissioned

A

P

I

I

I

L

264 Construction Management for Industrial Projects

Install components & system

I

I

I

A

A

L

V

Review RFIs and changes for impacts on Cx

A

I

I

1/s

S

L

S

V

Demonstrate operation of systems

I

P/I

I

P

L

V

Complete construction checklists as the work is accomplished

I

I

I

I

S

L

A

Continuously maintain the record drawings and submit as detailed in the contract documents

A

S

I

S

L

V

Coordinate functional testing for all commissioned systems & assemblies

I

I

I

P/A

I

s

S

L/A

Perform quality control inspections

I

I/P

L

S

P/I

Maintain record of functional testing

I

I

I

I/P

I

S

s

L

Prepare Cx Progress Report

A

I

I

I/P

I

P

s

L

Hold Construction Phase Cx meeting

P

P

P

P

P

P

p

L

Quality — From Theory to Reality 265

Legend

L = Lead P = Participate S = Support I = Inform A = Approve V = Verify

GSA

Project

Manager

GSA

Operating

Personnel

Customer

Agency

Reps

GSA

Technical

Experts

CM

Construction

Contractor

CxA

A/E

Maintain master Issues Lo

I

I

I

I

I

S

I

L

Review equipment warran­ties to ensure GSA responsi­bilities are clearly define

I

I

s

S

L

Implement training program for GSA Operating Personnel

I

P

P

I/S

p

s

s

L

Compile and deliver Turnover Package

A

A

s

s

L

S/V

Deliver Commissioning Record

A

P

P

I

s

S

S

L

Post-Construction Stag

Coordinate & supervise deficiency correction

A

P

I

I/S

L

S

I

Coordinate & supervise deferred & seasonal testing

A

P

I

S

I

Review & address outstanding issue

A

P

I

I/S

S

S

I