Review Submittals for Performance Parameters

As submittals for products and materials are received from contrac­tors, copies of submittals critical to the commissioning process shall be forwarded to the CxA.

In general the CxA is responsible to review the following types of submittals:

• Coordination drawings

• Redline as-builts

• Product data and key operations data submittals

• Systems manuals

• Training program

Clearly, the CxA cannot review every project submittal. The CxA’s review of submittals shall be limited to those items that are critical to the focus of the commissioning process. This review allows the CxA to check the submittals for adherence to the owner’s project requirements, basis of design, and project specifications. The CxA shall pay special attention to substitutions and proposed deviations from contract documents and the BOD. The CxA will only com­ment on submittals to the extent that there is a perceived deviation from the owners.