Update/Refine Commissioning Plan

Now that the Commissioning Agent is on board and has per­formed Design Stage reviews, the team realigns and updates the Commissioning Plan in preparation for the construction stage.

The Commissioning Team shall formally accept the updated Commissioning Plan before moving into construction. Further­more, all outstanding comments and issues relative to the CxA’s review of the design shall be resolved, and accepted changes shall be incorporated into the contract and construction bid documents.

• Commissioning team directory

• Commissioning process activities

• Roles and responsibilities

• Communication structures

• Commissioned systems and equipment

• Commissioning process schedule

• Appendices (owners project requirements, BOD, Design Review, Issues Log)