Measurement and payment

(1) Unwatering Phase I excavation.

(a) No measurement will be made for unwater­ing Phase I excavation.

(b) Payment for unwatering Phase I excavation will be made at the lump sum price and shall consti­tute full compensation for furnishing all plant, labor, materials, and equipment necessary to unwater Phase I excavation.

(2) Surface water control and sump pumping.

(a) No measurement will be made for surface water control and sump pumping.

(b) Payment for surface water control and sump pumping will be made at the lump sum price and shall constitute full compensation for furnishing all plant, labor, materials, and equipment for surface water con­trol and sump pumping, irregardless of the source of water.

(3) Deep dewatering wells.

(a) Dewatering wells will be measured for pay­ment on the basis of each well successfully completed and accepted by the Government.

(b) Payment at the contract unit price for instal­lation of dewatering wells shall constitute full compen­sation for furnishing all plant, labor, materials, and equipment for performing all operations necessary to install, develop, and test pump each well.

(4) Dewatering turbine pumps, engines, and acces­sories. /

(a) Dewatering turbine ршпріз, engines, and ac­cessories as specified on the drawings will be measured

for payment on the basis of each pump properly in­stalled and fully operational.

(b) Payment at the contract unit price for instal­lation of dewatering turbine pumps, engines, and ac­cessories shall constitute full compensation for fur­nishing all plant, labor, materials, and equipment for furnishing and installing the pumps and engines.

(5) Standby turbine pumps,

(a) Standby turbine pumps will be measured for payment on the basis of each complete pump placed on the jobsite.

ф) Payment at the contract unit price for fur­nishing standby turbine pumps shall constitute full compensation for furnishing the pumps and placing in appropriate storage. Each standby turbine pump shall include all components shown on the drawings includ­ing, but not limited to, 130 feet of column pipe and shafting, pump bowls, suction pipe, pump head, gear drive, and flexible coupling.

(6) Standby dieselpower units.

(а) Standby diesel power units will be measured for payment on the basis of each complete power unit placed on the jobsite.

(б) Payment at the contract unit price for fur­nishing standby diesel power units shall constitute full compensation for furnishing all plant, labor, mate­rials, and equipment for furnishing the diesel engines and placing in appropriate storage. Each standby die­sel power unit shall include all components shown on the drawings including the 110-horsepower diesel en­gine with clutch power takeoff and fuel tank.